Bolgrad Launches Hybrid Solar Plant with Oversized Battery: First Power in December
Codex Energy is completing construction of a 4.5 MW solar park paired with a 20 MWh battery storage system. Commercial generation is set to begin in December, with first investor payouts expected in Q1 2027.
Photo: Інші видання
Key points
- Codex Energy's Bolgrad park starts commercial generation in December 2024
- 20 MWh battery exceeds 4.5 MW solar capacity for winter effectiveness
- Project provides Odesa businesses alternative power source and boosts grid resilience
The Bolgrad energy park by Codex Energy is entering its final commissioning phase: civil works are finished on schedule and the technical team is finalizing grid-connection paperwork. Commercial operation is slated for December, when Ukrainian businesses will be able to purchase the output. Total investment in the project stands at €6.3 million.
Why the battery outrates the solar array
The plant's defining feature is an unconventional capacity ratio. The solar farm is rated at 4.5 MW, while the storage system delivers 6.3 MW with 20 MWh capacity. The design is driven by winter realities: December daylight in Odesa region lasts barely nine hours with a low sun angle, drastically cutting panel yield. The oversized battery captures the short-day harvest and discharges it during evening peak demand rather than at the moment of generation.
According to Codex Energy co-founder and director Oleksandr Hanchev, Bolgrad is the company's first full-cycle project from concept to commissioning. The storage-first approach aims to supply businesses with power exactly when they need it most.
Impact on local economy and energy security
Bolgrad's community of roughly 15,000 residents and its agriculture-and-processing-driven economy depend critically on reliable electricity. Grain elevators, cold stores, pumping stations and packing plants cannot afford downtime: even a few hours without power means spoiled produce, missed shipments and direct financial losses. The new park adds a procurement channel, diversifying energy sources for local enterprises.
Against the backdrop of sustained attacks on Ukraine's energy infrastructure, every distributed generator with its own reserve acts as an additional grid fuse. A single asset cannot guarantee zero outages, but generation next to the consumer and hours of stored energy markedly improve regional supply resilience. For investors, December marks the transition from construction site to revenue-generating asset, with first dividends anticipated in early 2027.
Source Інші видання — interfax.com.ua/news/press-release/1239364.html ↗
Read next
The Economist: Russia, China, Iran, and North Korea form a dangerous 'axis of cooperation'
Authoritarian regimes are coordinating their actions in technology, military intelligence, and sanctions evasion, creating significant challenges for global security.
💡TechInvestigation into the X-101 Missile Incident in Poland: New Details
Polish investigators confirmed that three Russian X-101 cruise missiles, manufactured in 2026, breached the country's airspace.
House of Culture director from the region impresses 'The Voice of Ukraine' coaches
Alona Kompaniets, who runs a local House of Culture, wowed the judges on the vocal show with her performance of the folk song 'Plyve Kacha'.
🚨EventsPolice search for suspects following deadly shooting in Kharkiv
On the evening of November 22, an unidentified person was shot dead in Kharkiv. A special police operation is underway to locate the perpetrators.
⚽SportUkrainian players lead Girona to victory in Segunda match
Vladyslav Vanat and Oleksandr Pishchur played pivotal roles in Girona's 2-1 victory over Eibar in the Spanish Segunda Division.
Rescue operation in Kyiv region: 7-year-old boy pulled from rubble after 14 hours
In the village of Dymer, rescuers saved a child who was trapped under the ruins of a house following a drone attack.